Physical Planning Unit is an arm of the College under Rectory saddled with the responsibility of conceptualizing, planning, executing and coordinating all physical development in the College. As an arm that deals with projects, its activities/operations is being managed by professionals and administrative staff. The office is located at the second floor, seven storey building of the College.
The Unit is to monitor the on-going projects in conjunction with the Project Consultants. The Physical Planning Unit (PPU) also interfaces between the Contractors, Suppliers and the Management.
The PPU is responsible for the documentation of papers to the Tenders’ Board as part of its responsibilities as the Secretary to the Tenders’ Board.
The Physical Planning Unit comprises of the following staff;
Projects
In order to accommodate the fast growing population and increase in the College carrying capacity, several infrastructural projects were conceptualized and the funding of such was sourced from the available resources are as stated below:
TETFund Projects
2011 TETFund Special Intervention
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Construction of a 1300 Seater Capacity Lecture Theatre |
Construction of a 1300 Seater Capacity Lecture Theatre |
August 2012 |
TETFUND |
Completed |
2 |
Construction of a 3-Storey Science Building |
Construction of a 3-Storey Science Building |
August 2012 |
TETFUND |
Completed |
3 |
Construction of School of Maritime Studies |
Construction of School of Maritime Studies |
August 2012 |
TETFUND |
Completed |
4 |
Construction of various farm structures for Department of Agriculture, Epe Campus. |
Construction of various farm structures for Department of Agriculture, Epe Campus |
|
|
|
4A |
Construction of Poultry House |
Construction of Poultry House |
August 2012 |
TETFUND |
Completed |
4B |
Construction of Cow free Stall Bam |
Construction of Cow free Stall Bam |
August 2012 |
TETFUND |
Completed |
4C |
Construction of Rabbit Shed |
Construction of Rabbit Shed |
August 2012 |
TETFUND |
Completed |
4D |
Construction of Smoke House |
Construction of Smoke House |
August 2012 |
TETFUND |
Completed |
4E |
Construction of Kitchen with Pavilion |
Construction of Kitchen with Pavilion |
August 2012 |
TETFUND |
Completed |
4F |
Construction of Sheep and Lamp shed |
Construction of Sheep and Lamp shed |
August 2012 |
TETFUND |
Completed |
4G |
Construction of Piggery House |
Construction of Piggery House |
August 2012 |
TETFUND |
Completed |
2011 / 2012 TETFund Projects
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Construction of a 3- Storey Building for Central Laboratory |
Construction of a 3- Storey Building for Central Laboratory |
June 2013 |
TETFUND |
Completed |
2 |
Procurement of X-Ray Machine |
Procurement of X-Ray Machine |
June 2013 |
TETFUND |
Completed |
3 |
Procurement of Equipment for Maritime Studies |
Procurement of Equipment for Maritime Studies |
June 2013 |
TETFUND |
Completed |
4 |
Procurement of Equipment for Various Department |
Procurement of Equipment for Various Department |
June 2013 |
TETFUND |
Completed |
5 |
Provision of Facilities for Department of Agriculture, Epe |
Provision of Facilities for Department of Agriculture, Epe |
June 2013 |
TETFUND |
Completed |
6 |
Furnishing of Technology building |
Furnishing of Technology building |
June 2013 |
TETFUND |
Completed |
7 |
Procurement of 150KVA Generator for Library |
Procurement of 150KVA Generator for Library |
June 2013 |
TETFUND |
Completed |
8 |
Procurement of Weaving Loom for Polymer & Textile Department |
Procurement of Weaving Loom for Polymer & Textile Department |
June 2013 |
TETFUND |
Completed |
9 |
Procurement of Tables |
Procurement of tables |
September 2013 |
TETFUND |
Completed |
10 |
Procurement of drawers, books, support, table & chairs |
Procurement of drawers, books, support, table & chairs |
September 2013 |
TETFUND |
Completed |
11 |
Procurement of library software |
Procurement of library software |
September 2013 |
TETFUND |
Completed |
12 |
Procurement of comfortable reading chairs |
Procurement of comfortable reading chairs |
September 2013 |
TETFUND |
Completed |
13 |
Procurement of 321 different titles of assorted booksPOLY/Yaba /TETF/LIB/2011-2012/15 |
Procurement of library books |
September 2013 |
TETFUND |
Completed |
14 |
Procurement of 393 different titles of assorted books POLY/Yaba/TETF/LIB/2011-2012/13 |
Procurement of library books |
September 2013 |
TETFUND |
Completed |
15 |
Procurement of 291 different titles of assorted books POLY/Yaba/TETF/LIB/2011-2012/14 |
Procurement of library books |
September 2013 |
TETFUND |
Completed |
2013 TETFund Special Intervention Projects |
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Procurement, Installation and commissioning of Interactive Board |
Procurement, Installation and commissioning of Interactive Board |
March 2013 |
TETFUND |
Completed |
2 |
Procurement, Installation and commissioning of Computer systems |
Procurement, Installation and commissioning of Computer systems |
March 2013 |
TETFUND |
Completed |
3 |
Procurement, Installation and commissioning of Analytical Laboratory Equipment |
Analytical Equipment |
November 2014 |
TETFUND |
Completed |
4 |
Procurement, Installation and commissioning of Science Equipment |
Science Equipment |
November 2014 |
TETFUND |
Completed |
5 |
Procurement, Installation and commissioning of Engineering Equipment |
Engineering Equipment |
November 2014 |
TETFUND |
Completed |
6 |
Procurement of Food processing and Engineering furniture, set of furniture for Central |
Furniture |
November 2014 |
TETFUND |
Completed |
7 |
Procurement of 4 Nos 60 Seater Buses |
Buses |
November 2014 |
TETFUND |
Completed |
2013TETFund Special Intervention Projects (Additional) |
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Procurement, Installation and commissioning of Analytical Laboratory Equipment |
Analytical Equipment |
December 2014 |
TETFUND |
Completed |
2 |
Procurement, Installation and commissioning of other Laboratory Equipment |
Equipment |
December 2014 |
TETFUND |
Completed |
3 |
Procurement, Installation and commissioning of Engineering Equipment |
Engineering Equipment |
December 2014 |
TETFUND |
Completed |
4 |
Procurement, Installation and commissioning of Chemical Engineering Equipment |
Engineering Equipment |
December 2014 |
TETFUND |
Completed |
5 |
Procurement, Installation and commissioning of Marine Engineering Equipment |
Equipment |
December 2014 |
TETFUND |
Completed |
6 |
Procurement, Installation and commissioning of Generator |
Generators |
December 2014 |
TETFUND |
Completed |
7 |
Procurement, Installation and commissioning of Computers Accessories |
Computers |
December 2014 |
TETFUND |
Completed |
8 |
Supply / Delivery and Installation of Furniture |
Furniture |
December 2014 |
TETFUND |
Completed |
2013 - 2014 (Merged) TETFund Annual Intervention Projects |
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1a |
Construction of One-Storey Block of Classrooms/Laboratories/Staff Offices at Epe Campus - CONTRACT NO: YCT/LAGOS/TETF/13-14/01A |
Construction of One-Storey Block of Classrooms/Laboratories/Staff Offices at Epe Campus |
December, 2015 |
TETFUND |
Completed |
1b |
Construction of One-Storey Block of Classrooms/Laboratories/Staff Offices at Epe Campus - CONTRACT NO: YCT/LAGOS/TETF/13-14/01B |
Construction of One-Storey Block of Classrooms/Laboratories/Staff Offices at Epe Campus |
December, 2015 |
TETFUND |
Completed |
2 |
Construction of 1 No Three-Storey Building of Laboratories and Offices at Yaba Campus - CONTRACT NO. YCT/YABA/TETF/13-14/02 |
Construction of 1 No three-Storey Building of Laboratories and Offices at Yaba Campus |
December, 2015 |
TETFUND |
Completed |
3 |
Supply and installation of Equipment for Civil Engineering Department - CONTRACT NO: YCT/YABA/TETF/13-14/03 - |
Supply and installation of Equipment for Civil Engineering Department - |
December, 2015 |
TETFUND |
Completed |
4 |
Supply and installation of Welding and Fabrication Equipment -CONTRACT NO: YCT/YABA/TETF/13-14/04 |
Supply and installation of Welding and Fabrication Equipment - |
December, 2015 |
TETFUND |
Completed |
5 |
Supply and Installation of equipment for Electrical Electronics Engineering Department - CONTRACT NO: YCT/YABA/TETF/13-14/05 |
Supply and Installation of equipment for Electrical Electronics Engineering Department |
December, 2015 |
TETFUND |
Completed |
6 |
Supply and installation of equipment for Mechatronics Engineering Department - CONTRACT NO: YCT/YABA/TETF/13-14/06 |
Supply and installation of equipment for Mechatronics Engineering Department |
December, 2015 |
TETFUND |
Completed |
7 |
Supply and installation of equipment for Mechanical Engineering Department - CONTRACT NO: YCT/YABA/TETF/13-14/07 |
Supply and installation of equipment for Mechanical Engineering Department - |
December, 2015 |
TETFUND |
Completed |
8 |
Supply and installation of equipment for Chemical Engineering Department - CONTRACT NO: YCT/YABA/TETF/13-14/08 |
Supply and installation of equipment for Chemical Engineering Department |
December, 2015 |
TETFUND |
Completed |
9 |
Supply and installation of equipment for Agriculture & Bio-Environmental Engineering Department - CONTRACT NO: YCT/YABA/TETF/13-14/09 |
Supply and installation of equipment for Agriculture & Bio-Environmental Engineering Department |
December, 2015 |
TETFUND |
Completed |
10 |
Supply and installation of equipment to Soil Science Laboratory (Department of Agric Technology) - CONTRACT NO: YCT/YABA/TETF/1314/0 |
Supply and installation of equipment to Soil Science Laboratory (Department of Agric Technology) |
December, 2015 |
TETFUND |
Completed |
11 |
Supply and installation of equipment to type Crop protection Laboratory, Entomology Physiology (Department of Agric Technology -CONTRACT NO: YCT/YABA/TETF/13-14/11 |
Supply and installation of equipment to type Crop protection Laboratory, Entomology Physiology (Department of Agric Technology |
December, 2015 |
TETFUND |
Completed |
12 |
Supply and installation of equipment to General Laboratory (Dept. of Agric Technology) - CONTRACT NO: YCT/YABA/TETF/13-14/12 |
Supply and installation of equipment to General Laboratory (Dept. of Agric Technology) |
December, 2015 |
TETFUND |
Completed |
13 |
Supply and installation of equipment to the (Dept. of Agric Technology) - CONTRACT NO: YCT/YABA/TETF/13-14/13 |
Supply and installation of equipment to the (Dept. of Agric Technology |
December, 2015 |
TETFUND |
Completed |
14 |
Supply, Installation and Commissioning of Laboratory equipment for College Medical Centre, and 1 No Ambulance - CONTRACT NO: YCT/YABA/TETF/13-14/14 |
Supply, Installation and Commissioning of Laboratory equipment for College Medical Centre, and 1 No Ambulance |
December, 2015 |
TETFUND |
Completed |
15 |
Supply and Installation of Equipment for Mass Communication Department -CONTRACT NO:YCT/YABA/TETF/13-14/15 |
Supply and Installation of Equipment for Mass Communication Department |
December, 2015 |
TETFUND |
Completed |
16 |
Supply of furniture for Staff Offices, Classrooms and Laboratories - CONTRACT NO: CT/YABA/TETF/13-14/16 |
Supply of furniture for Staff Offices, Classrooms and Laboratories |
December, 2015 |
TETFUND |
Completed |
17 |
Supply of Pneumatic Scaffolding for High rise building - CONTRACT NO: YCT/YABA/TETF/13-14/17 |
Supply of Pneumatic Scaffolding for High rise building |
December, 2015 |
TETFUND |
Completed |
18 |
Supply and Installation of Generators CONTRACT NO: YCT/YABA/TETF/13-14/18 |
Supply and Installation of Generators |
December, 2015 |
TETFUND |
Completed |
19 |
Supply of Fire Fighting Truck - CONTRACT NO: YCT/YABA/TETF/13-14/19 |
Supply of Fire Fighting Truck |
December, 2015 |
TETFUND |
Completed |
2013 - 2014 (Merged) TETFund Annual Intervention in Library Development
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Procurement of Assorted Books (Lot 1.1) - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/01 |
Procurement of Assorted Books |
October, 2016 |
TETFUND |
Completed |
2 |
Procurement of Assorted Books (Lot 1.2) - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/01 |
Procurement of Assorted Books |
September, 2015 |
TETFUND |
Completed |
3 |
Procurement of Assorted Books (Lot 1.3) - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/01 |
Procurement of Assorted Books |
December, 2015 |
TETFUND |
Completed |
4 |
Procurement of Assorted Books (Lot 1.4) - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/01 |
Procurement of Assorted Books |
December, 2015 |
TETFUND |
Completed |
5 |
Procurement of Assorted Journals - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/02 |
Procurement of Assorted Journals - |
December, 2015 |
TETFUND |
Completed |
6 |
Procurement of Assorted Reference Books - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/03 |
Procurement of Assorted Reference Books |
December, 2015 |
TETFUND |
Completed |
7 |
Procurement of Computers - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/04 |
Procurement of Computers - |
December, 2015 |
TETFUND |
Completed |
8 |
Procurement of UPS - CONTRACT NO: TETF/POLY/YABA/LIB/13-14/05 |
Procurement of UPS |
December, 2015 |
TETFUND |
Completed |
9 |
Procurement of Computer Printers - CONTRACT NO: TETF/POLY/YABA/LIB/13-14/08 |
Procurement of Computer Printers - |
December, 2015 |
TETFUND |
Completed |
10 |
Procurement of Library Furniture (lot 7.1) - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/07 |
Procurement of Library Furniture |
December, 2015 |
TETFUND |
Completed |
11 |
Procurement of Library Furniture (lot 9.2)- CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/07 |
Procurement of Library Furniture |
December, 2015 |
TETFUND |
Completed |
12 |
Procurement of library furniture CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/07(lot 9.3) |
Procurement of Library Furniture |
December, 2015 |
TETFUND |
Completed |
13 |
Procurement of Library Furniture (lot 7.3) - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/07 |
Procurement of Library Furniture |
September, 2015 |
TETFUND |
Completed |
14 |
Procurement of Digital Printing Machine and Hardcover Notes - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/08 |
Procurement of Digital Printing Machine and Hardcover Notes |
December, 2015 |
TETFUND |
Completed |
15 |
Procurement of Binders - CONTRACT NO: TETF/POLY/YABA/LIB/13-14/09 |
Procurement of Binders |
December, 2015 |
TETFUND |
Completed |
16 |
Procurement of P-Touch Desk - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/10 |
Procurement of P-Touch Desk |
December, 2015 |
TETFUND |
Completed |
17 |
Procurement of Book Display Rack-Mobile Stay Wall Rotating Tower - CONTRACT NO: TEFT/POLY/YABA/LIB/13-14/11 |
Procurement of Book Display Rack-Mobile Stay Wall Rotating Tower |
September, 2015 |
TETFUND |
|
18 |
Procurement of Equipment and Installation of Band-width CONTRACT NO: TEFT/POLY/YABA/ LIB/13-14/12 |
Procurement of Equipment and Installation of Bandwidth |
December, 2015 |
TETFUND |
Completed |
Year 2015 – 2018 (Merged) TETFund Annual Intervention
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Supply, Installation of Furniture & Fittings to Lecture Theatre |
Supply, Installation of Furniture & Fittings to Lecture Theatre |
September, 2019 |
TETFUND |
On-going |
2 |
Supply, Installation, Testing & Training on the use of Equipment for various Departments. |
Supply, Installation, Testing & Training on the use of Equipment for various Departments. |
September, 2019 |
TETFUND |
Completed |
3 |
Supply & Installation of Furnishing & Fitting for Engineering Block |
Supply & Installation of Furnishing & Fitting for Engineering Block |
September, 2019 |
TETFUND |
Completed |
4 |
Supply, Installation, Testing & Training on the use of Equipment for various Departments. |
Supply, Installation, Testing & Training on the use of Equipment for various Departments. |
September, 2019 |
TETFUND |
Completed |
5 |
Supply, Installation, Testing & Training on the use of Equipment for various Departments. |
Supply, Installation, Testing & Training on the use of Equipment for various Departments. |
September, 2019 |
TETFUND |
Completed |
6 |
Supplementary equipment, supply of computers and computer accessories |
Supply of computers and computer accessories |
September, 2019 |
TETFUND |
Completed |
7 |
Construction of 2-Storey Office Building for School of Management and Business Studies |
Construction of 2-Storey Office Building for |
November, 2019 |
TETFUND |
On-going |
8 |
Construction of lecture theatres for School of Management & Business Studies |
School of Management & Business Studies |
November, 2019 |
TETFUND |
On-going |
9 |
Rehabilitation and refurbishment of Engineering Building |
Renovation of Engineering Building - |
November, 2019 |
TETFUND |
Completed |
2016-2019 (Merged) TETFund Maintenance Intervention Project
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Rehabilitation and refurbishment of the ETF building |
Rehabilitation and refurbishment |
February 2021 |
TETFUND |
On-going |
2017 TETFund Zonal Intervention
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
|
|
July, 2019 |
TETFUND |
Completed |
|
|
|
July, 2019 |
TETFUND |
Completed |
2016-2018 Merged TETFund ICT Intervention
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Design and training for College Website |
Website design and training Nigeria Ltd |
December 2019 |
TETFUND |
Completed |
2018 TETFund Zonal Intervention
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
|
|
January, 2020 |
TETFUND |
Completed |
|
|
|
January, 2020 |
TETFUND |
Completed |
2019-2020TETFund Merged Annual Intervention
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE-MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Construction of SMBS Classrooms Ph. 2 for YCTatYaba Campus |
Construction of SMBS Classrooms Ph. 2 for YCTatYaba Campus |
July 2021 |
TETFUND |
On-going |
2 |
Construction of School of Technical Education(STE) Building at Epe |
Construction of School of Technical Education(STE) Building at Epe |
December 2019 |
TETFUND |
On-going |
2019-2020 TETFund Projects
S/N |
PROJECT TITLE |
PROJECT DESCRIPTION |
COMMENCE- MENT DATE |
SOURCE OF FUNDS |
PRESENT STATUS |
1 |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment |
July 2019 |
TETFUND |
Completed |
2 |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 5) |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 5) |
July 2019 |
TETFUND |
Completed |
3 |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 3) |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 3) |
January 2020 |
TETFUND |
Completed |
4 |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 4) |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 4) |
July 2019 |
TETFUND |
Completed |
5 |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 1) |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 1) |
July 2019 |
TETFUND |
Completed |
6 |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 2) |
Award of Contract for the Procurement and Installation of Various Laboratories and Workshop Equipment (Lot 2) |
July 2019 |
TETFUND |
Completed |
Arc.SheriffdeenAyodele-Ojamnia
Director, Physical Planning Unit